Cost to complete HS2 hits £102.7bn

Grant Prior 19 minutes ago
Share

The cost of completing HS2 has risen again with a new estimated budget in the range of £ 87.7 – 102.7 billion.

The latest numbers were unveiled by Transport Secretary Heidi Alexander as she also confirmed the opening of the full route between London Euston to Birmingham Curzon Street and to the connection to the West Coast Main Line at Handsacre Junction will not happen until “between May 2040 and December 2043.”

Top speeds on the route will also be reduced to cut costs.

HS2 CEO Mark Wild has been working on rescoping the project including a complete cancellation which was dismissed due to an estimated remediation cost of £58bn for work completed so far.

Alexander said: “The reset work also makes clear that progress on finishing the civil engineering for the entire line of route is at least four years behind the original schedule, and that the time required to test and commission HS2 to ensure a reliable and safe service was underestimated by another three years.

“The number of years left to complete the programme is roughly the same as when construction started in 2020, and it is likely we will need to spend the same amount as has already been spent to date.

“It is now imperative that we proceed with the final stages of the HS2 reset so that the programme is brought under control and delivered sensibly going forward.

“Under new leadership, HS2 Ltd is putting construction back in logical order, strengthening commercial controls, restructuring the organisation, and rebuilding the partnership with government.

“HS2 Ltd’s new management team inherited a challenging commercial position. Prior to the reset, commercial capabilities and the management of HS2’s construction contracts were not effective.

“HS2 Ltd’s ability to settle commercial matters progressively and contemporaneously had deteriorated and become insufficient over recent years. Consequently, large backlogs had been allowed to develop in relation to cost verification, cost finalisation and contract change.

“HS2 Ltd has since concentrated on strengthening its commercial controls. New commercial roles have been created to focus on cost verification and contract management, to scrutinise every payment application, to challenge contractor claims, and to manage contracts in taxpayers’ interests. These improvements must be fully embedded in the company, and endure beyond completion of the reset, to the conclusion of the programme.

“HS2 Ltd is also engaging with its key supply chain partners to review contracts, close out historic payments only where appropriate and justified, and seek opportunities to incentivise improved performance. This work will be critical to stabilising costs and enabling us to make the spend on HS2 as efficient as possible.”

Latest news

Cost to complete HS2 hits £102.7bn

Government vows to get tough on contract claims as budget busted again
32 minutes ago

Mace Construct chief executive to step down

Jason Millett to leave in December but retain board seat at Mace Consult
7 hours ago

Over 90 jobs axed as Falkirk steelwork firms collapse

Administrators called in at AIM Engineering & Fabrication Group and Hescott Engineering
6 hours ago

Keady Construction lands £150m Stockport resi scheme

Construction to start in first quarter of 2027 for developer Amstone
6 hours ago

Forterra plans brick and block price hikes

Materials giant to implement "pricing surcharges" from June
6 hours ago

Renew snaps up electricity design specialist EDES

Engineering contractor targets grid boom with latest takeover
6 hours ago

Sixteen win £1bn Southern Gas Networks deal

Clancy Docwra and Network Delivery Associates win places on all four lots
7 hours ago

Kier submits plan for £60m Ellesmere Port school rebuild

RAAC-hit 1,000 place Catholic high school set for full demolition and replacement
7 hours ago

Statom Holdings posts increased turnover and profits

Results for whole group highlight landmark year of growth
22 hours ago

Morrisroe order book jumps 40% after Villa Park and Battersea wins

Diversified concrete frame specialist banks £340m order book after margin recovery last year
1 day ago

Trial date set after passer-by killed by falling window pane

Four firms to appear in court after glass fell 15 storeys from luxury tower
1 day ago

Norwich’s first build-to-rent scheme approved

£80m Victoria Gardens plan will deliver 432 rented homes
1 day ago

Dalkia lands M&E deal at £300m Children’s Cancer Centre

Major package award at Sisk site as piling work due to complete this month
1 day ago

London office fit-out second most pricey in the world

High-spec fit-outs now cost nearly £4,400 per sq m as occupiers chase top quality workspace
4 days ago

Developers called up for £10bn Old Oak mega-scheme

Race starts to find developer partner by spring 2027 to deliver 8,000 homes
4 days ago

Speller Metcalfe replaces Curo on £18m leisure job

Fenland council acts swiftly to keep Manor Leisure Centre on track
4 days ago

Bachy and Kilnbridge team up for ground-to-frame offer

New UrbanCore venture to target complex basement and structural packages
4 days ago

Statom builds £617m order book after board strengthened

Essex contractor reshapes around integrated engineering and self-delivery model
4 days ago

Lovell signs off £1bn Birmingham estate regen deal

Developer to lead 3,500-home rebuild of Druid’s Heath over 20 years
5 days ago

Legendre to start £70m Mayfair office revamp

Main construction begins in June at 50 Stratton Street site
5 days ago

Road worker loses leg in milling machine

Court hears how worker became entangled in machine while road planing
5 days ago

Costain on track for 4% margin as workload builds

Contractor expects revenue and profit growth this year ahead of bigger 2027 uplift
5 days ago

Falkirk steelwork firm workers protest after wages fail to land

Workers gather at Hescott Engineering as fears grow over firm’s future
5 days ago

Ageing M53 bridges first in line for £1bn motorway structures repair

Four bridge decks to be replaced in three-year Merseyside and Cheshire upgrade
5 days ago

Landsec flags more delays on major housing starts

Developer waiting for policy concessions to make schemes more profitable
5 days ago

Plans in for £100m Buxton town centre reboot

Capital&Centric finalises plan for Spring shopping centre redevelopment
5 days ago

Ex-Skanska VP joins M Group as energy infrastructure chief

Former COO Andrew English brought in to drive sector growth
6 days ago

Vistry warns first-half profits to be hit by discount drive

New Vistry chief starts operational review as cash drive shifts private homes stock
6 days ago

Strabag UK gears up for civils work surge next year

Trio of major tunnelling jobs to drive revenue to £1bn target
6 days ago

Glencar revealed as builder of £50m Minecraft World

Contractor confirmed on latest attraction at Chessington World of Adventures
6 days ago