Sir Robert McAlpine suffers £90m loss

Aaron Morby 9 years ago
Share

Sir Robert McAlpine has been hit by a series of problem contracts plunging the contractor into a £89.7m pre-tax loss in 2014.

The firm said it had been hit by several poorly performing contracts at the UK construction business, including a significant loss on its Fitzroy Place project  on the site of the former Middlesex Hospital in London.

The £160m Fitzrovia offices and luxury flats project is nearly complete and McAlpine said it had provided for all the loses.

Fitzroy place

McAlpine’s mounting problems last year are understood to have been behind its decision to pull off the Centre Point tower residential conversion project in London for developer Almacantar.

The firm said it had now restructured its London operations, introduced more robust governance procedures and established a cost efficiency programme. This includes rolling out a technology upgrade to enhance operational productivity.

The extent of the private construction group’s woes were revealed in holding company Newarthill’s accounts, which include separate property and PPP assets, posted at Companies House.

This showed the entire group contracting activities ran up total operating losses of £108m, including overseas operations on turnover flat at £862m in the year to October 2014.

The Newarthill Group has now suffered two bad years of losses after the high of Sir Robert McAlpine’s successful projects for the London Olympic Games.

Newarthill incorporating Sir Robert McAlpine
2014 profit 2013 profit 2014 turnover 2013 turnover
Contracting -£108m -£42m £819m £810m
Property+JVs £2.2m £1.7m £13m £13m
PPP + JVs £22m £64m £232m £75m

 

Director Cullum McAlpine said: “2014 was a challenging year and in addition to the general market pressures we identified some weaknesses within our own operations that contributed to delays and cost escalations, resulting in losses from on one project in particular.

“These processes – risk management during tendering and the management of our design responsibilites and changes – have been reviewed and corrected with a restructure of our management framework.

McAlpine’s loss-making Bermuda hospital job was completed last June and the firm said the focus had now moved to recovery of losses from other parties involved in the project.

In the 2013 accounts McAlpine booked a £41m loss, mainly due to problems on a £176m joint venture contract to build Bermuda’s King Edward VII Memorial Hospital.

During the year, McAlpine sold Colchester garrison PFI and Fife Schools PPP which raised £41m in net cash and achieved a profit on sale £31.4m.

Group cash balances at year-end were down to £220m from £262m in 2013.

Latest news

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
2 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
2 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
2 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
2 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
2 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
2 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
2 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
3 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
3 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
3 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
3 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
3 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
3 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
4 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
4 days ago

Go-ahead for £100m Liverpool Love Lane flats

500-flat scheme will be built across four blocks in Vauxhall area of city
4 days ago

Unions win HS2 site access battle at Old Oak Common job

Skanska, Costain, Strabag JV now the last denying unions access to HS2 sites
4 days ago

Contractors jack 1,100t viaduct into place in 13-hour operation

158m-long composite deck structure jacked into place 10-hours ahead of schedule
4 days ago

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
4 days ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
4 days ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
5 days ago

Fear of supply chain failures boosting collaboration

Procurement survey also reveals project bank account use is rising
5 days ago

Wates sets up business to target 160,000 mouldy social homes

Healthy Homes service will be offered to social landlords across England
5 days ago

Higgins wins £75m Peabody Passive House job

Latest phase of Deptford Landings to start construction
5 days ago

Contractors and unions agree Sizewell C working deal

New deal offers improved sick pay and parental leave over Hinkley Point deal
5 days ago

Competition chiefs win legal fight for more construction raids

High Court rules CMA officials can raid a domestic property as part of investigation
5 days ago

More Osborne companies file administration notices

Three more divisions lodge notices with court
6 days ago

McLaren wins multi-storey urban logistics contract

South London win with British Land is pioneering urban logistics hub
6 days ago

Big social housing schemes at risk over funding uncertainty

Housing associations warn uncertainty over public funding beyond 2026 is curbing new schemes
6 days ago

Kier wins Worcestershire town centre renewal

Firm secures Bromsgrove commercial and cultural hub project
6 days ago

Contractor services