Crisis-hit Carillion has revealed the full-extent of its losses this morning, which have now spiralled to £1.15bn.

Keith Cochrane, Interim Chief Executive, reveals Carilllion's problems are bigger than first thought
Keith Cochrane, Interim Chief Executive, reveals Carilllion's problems are bigger than first thought

In delayed half-year results, Carillion said it has taken a further £200m of writedowns on problem contracts, this time at the support services division.

These come on top of the £845m writedown suffered on construction contracts first revealed in July, which remain contained after further in-depth reviews of the construction book.

A group strategic review has set fresh stringent selectivity criteria for projects to support its new focus on core markets, leading to the removal of more than £14bn from Carillion’s opportunity pipeline.

This morning, Keith Cochrane, interim chief executive, launched an emergency cost-cutting and restructuring programme, expected to cost up to £100m by the end of this year.

Deep staff cuts will focus on stripping out layers of management between the delivery end of the business and senior management to help strengthen controls.

Going forward he aims to have no more than six layers of management from the site worker to the chief executive. In some parts of the business this presently extends to up to 12 management tiers.

This should remove £75m of ongoing cost, mainly from the UK, which accounts for £267m of group overhead.

He said: “This is a disappointing set of results which reflects the issues we flagged in July and the additional £200m provision for our support services business that we have announced today.

“Our focus is to complete the disposal programme, accelerate our action to take cost out of the business and get our balance sheet back to a place where it can support Carillion going forward.

“No one is in any doubt of the challenge that lies ahead. We have made an encouraging start and the ambition is there to build on that progress.”

He added that Carillion had the support of its five core banks and had agreed a further £140m committed facility, as it braced for average net borrowing to soar to between £825m and £850m by the full year.

This implies that second half average borrowing will rise to £1bn.

The emergency cash injection must be reduced to £100m by April 2018 and is repayable by December 2018.

Borrowing is expected to rise as Carillion works through problem contracts completing by the year end.

The new management team’s review of the entire business after uncovering significant problems on construction contracts unearthed losses on 23 of its 600 support services contracts.

The latest £200m provision includes £91m for underperforming contracts that Carillion will now exit. 

A further £56m for underperforming contracts where performance has been revised and £53m for contracts where a more realistic view of what will be received has been taken.

Carillion said it was still in talks to sell its UK healthcare arm and its Canadian business and expected sell-offs to raise £300m, up from an earlier target of £125m.

The firm said it had also taken an impairment charge of £134m on its UK and Canadian construction businesses.

Carillion is being restructured in four UK operating division from October.

New operating structure

Infrastructure – support services and construction primarily for transport infrastructure. Annual revenue is expected to be £800m, with a medium-term target margin of 3% to 4%.

Central Government – support services for the Ministry of Defence and other Central Government Departments. Expected revenue £800m, with a medium term target margin of 5% to 6%. 

Corporate and Regions – support services for corporate customers and regional public authorities. Annual revenue of £800m, with target margin of 6.5% to 7.5%. 

Building – construction for select public and private sector customers with annual revenue of £600m, and target margin of 2% to 3%.

Revenue for the full-year is forecast to fall from £4.8bn-£5bn to between £4.6bn-£4.8bn.

Cochrane said: “A number of actions are being undertaken urgently to address liquidity and rebuild the balance sheet, with which progress to date is positive.

“Nevertheless, transformation of the business, including a radical change in culture, will take three to five years.”

Latest news

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
2 mins ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
1 min ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
7 mins ago

Olympian Homes gets go-ahead Bristol’s tallest building

Work on student and co-living towers to start this summer
40 mins ago

ISG gets nod to start £20m Glamorgan school job

Ysgol y Deri specialist needs school is to built at Cosmeston, near Penarth
34 mins ago

Walker Modular lands £5m bathroom pod contract

Specialist to work with Graham and Watkin Jones on major build-to-rent scheme

Banned building boss jailed for fraud

Court hears how disqualified director siphoned off cash from new housing company
29 mins ago

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
3 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
3 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
3 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
3 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
3 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
3 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
3 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
4 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
4 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
4 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
4 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
4 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
4 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
5 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
5 days ago

Go-ahead for £100m Liverpool Love Lane flats

500-flat scheme will be built across four blocks in Vauxhall area of city
5 days ago

Unions win HS2 site access battle at Old Oak Common job

Skanska, Costain, Strabag JV now the last denying unions access to HS2 sites
5 days ago

Contractors jack 1,100t viaduct into place in 13-hour operation

158m-long composite deck structure jacked into place 10-hours ahead of schedule
5 days ago

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
6 days ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
6 days ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
6 days ago

Fear of supply chain failures boosting collaboration

Procurement survey also reveals project bank account use is rising
6 days ago

Wates sets up business to target 160,000 mouldy social homes

Healthy Homes service will be offered to social landlords across England
6 days ago

Contractor services