Concrete problems hit Hinkley Point tunnels

Grant Prior 7 years ago
Share

Contractors at Hinkley Point will have to replace 150 cubic metres of concrete poured on the site as part of work to form tunnels to contain pipes and cables.

Aerial view of the north office and galleries under construction
Aerial view of the north office and galleries under construction

Problems have been identified in sections of the concrete base slabs constructed above the galleries sections of tunnels which will contain site infrastructure.

The Enquirer understands that the problem concrete is local to a small stretch of the 8km network of galleries tunneling.

Only 150 cubic metres of material are affected from the first 60,000 cubic metres poured on the site so far.

Nothing has been built on the slab and it does not form part of the foundations for the main nuclear power plant building where work is not due to get underway for 18 months.

A joint venture of Kier and Bam Nuttall is main contractor on the site earthworks package.

GetImage-1

Work underway last month in the galleries

Hinkley delivery director Nigel Cann said: “We have decided to replace a small area of concrete poured as part of the work to create tunnels for the pipes and cables.

“This is in line with the uncompromising attitude to quality taken at the Hinkley Point C Project.

“It is a very small proportion of the concrete poured on site so far and has no impact on the project schedule.”

Site Progress so far:

2,000 workers are on site every day, 65,000 meals every month needed to feed the growing workforce.

1,500 bed “Campus” accommodation for workers under construction with 500 beds on the site and 1,000 in Bridgwater – supplied by Newark-based Caledonian Modular .

76 apprentices are already working on the project, which will create up to 1,000 apprenticeships during the build.

4 million cubic metres of earth have been excavated – that’s enough to fill Wembley Stadium.

Two concrete batching plants are now complete. Up to 2,000 tonnes of concrete a day can be produced on site. At least 3 million tonnes of concrete will be used – 75 times more concrete than was used to build the Millennium Stadium in Cardiff.

10,000 tonnes of rock has already been delivered by ship from Pembroke, for the site’s new 13.5 metres high seawall.

29km of ground nails have been installed – enough to loop the perimeter of Hyde Park six times. The steel rods, each measuring up to 12 metres long, are used to stabilise the ground. A total of 110km will be used during construction.

Project remains on track to meet the 64% UK supply contribution with nearly £9bn of contracts signed since final approval. The latest contract with ABB Group was signed last month for the main power transmission systems for both reactors.

49 piles have been installed for the 500m temporary jetty in the Bristol Channel. Each pile – the foundation legs for the jetty – is 36 metres long, 3.6 metres in diameter and weighs in at 140 tonnes. The jetty will allow 80% of the aggregate to be brought in by sea rather than by road and is due to be completed next year. Devon engineering firm Blackhill worked on its largest-ever project involving 550 tonnes of steel for the jetty.

Dozens of cranes of all sizes are already on site alongside 200 pieces of large-scale construction equipment, ranging from excavators capable of moving 30 tonnes of earth in a single scoop to giant dumper trucks. The tallest ‘tower’ crane is 40 metres tall and can lift 16 tonnes. At peak construction there will be 50 ‘tower’ cranes at site.

£15 million is being invested into education, employment and skills to help inspire the next generation and provide people with the necessary training and support to help them into long term careers. Multi-million pound investments into a Construction Skills Centre and an Energy Skills Centre are not only ensuring that local people are equipped with the skills they need for the future, but helping to fill a national skills gap.

Latest news

Go Modular Technologies files administration notice

Southampton bespoke volumetric specialist employs around 60 staff
1 hour ago

Cladding firm went down owing supply chain £7.7m

Debts revealed at Everton stadium cladding contractor Alucraft Systems Ltd
2 hours ago

Rydon dogged by legacy fire safety remediation costs

£19m spent on fire safety remediation work to date
2 hours ago

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
4 days ago

Trio of builders win King’s Award for sustainability

Henry Brothers, Willmott Dixon and ZED Pods recognised for sustainability
42 mins ago

Kent police seize huge haul of stolen site tools

Hunt for power drill fitted with tracker busts tool theft ring
1 hour ago

Robertson names new Northern construction chiefs

Ian Phillips promoted and Ricky Brown joins from Morgan Sindall
2 hours ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
4 days ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
4 days ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
4 days ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
4 days ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
5 days ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
5 days ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
5 days ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
5 days ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
6 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
5 days ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
6 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
5 days ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
5 days ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
6 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
6 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
7 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
6 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
6 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
6 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
1 week ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
1 week ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
1 week ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
1 week ago

Contractor services