Brickwork contractors facing mortar rationing

Aaron Morby 3 years ago
Share

Brickwork contractors are warning projects could grind to a halt because of rationing of bulk mortar supplies in the face of deepening cement shortages.

Brickwork contractors sound the alarm over mortar shortages
Brickwork contractors sound the alarm over mortar shortages

Bulk mortar suppliers have been put on allocation by major cement suppliers limiting their ability to manufacture and supply.

One dry mortar supplier Remix temporarily stopped taking orders this week although it hopes to get back on track next week.

Another big industry supplier Euromix has written to customers warning of disruption to supplies.

Kevin Flahive,  director of Watford firm Flahive Brickwork, said: “We started to see mortar silo refill lead times go from 4 days to 2 weeks.

“Now we’re are being told there is an issue with cement supplies and we could only be getting 60% of what we want.”

He added: “We’ve come very close to running out and another brickwork firm I know had to stop work last week.”

Eve Livett, Chief Executive Officer of the Association of Brickwork Contractors, said: “The majority of our 30 member contractors are experiencing problems with supply.

“If this continues it is going to scupper progress of works.

“It is vital that the wider industry be made aware of this so that a collaborative approach can be made with main contractors and their brickwork subcontractors.”

Supplier CPI Euromix’s managing director, Larry Dale said: “With immediate effect, our principle cement supplier has placed CPI and other customers on allocation, this will limit our ability to manufacture and supply mortar in certain locations.

“We will endeavour to provide the best service that we can, however these new production constraints will inevitably cause disruption in our ability to supply.

“We will provide the best information we can at the time of ordering in terms of indicative order call off times, we very much hope that this is a short term issue but in any event is out of our control at this time.”

Mineral Products Association chief executive Nigel Jackson, speaking on behalf of cement suppliers, said that a mix of high demand, kiln shutdowns for maintenance and trouble finding hauliers was causing localised delays.

“Where demand exceeds supply capacity longer lead times may be expected.

“As production catches up it shouldn’t be long before supplies are back to normal depending on how long this surge in pent-up demand actually lasts and subject to transport availability.”

Latest news

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
14 hours ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
16 hours ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
22 hours ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
23 hours ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
2 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
22 hours ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
21 hours ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
22 hours ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
2 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
2 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
2 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
3 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
2 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
3 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
2 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
3 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
3 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
3 days ago

Olympian Homes gets go-ahead for Bristol’s tallest building

Work on student and co-living towers to start this summer
3 days ago

ISG gets nod to start £20m Glamorgan school job

Ysgol y Deri specialist needs school is to built at Cosmeston, near Penarth
3 days ago

Walker Modular lands £5m bathroom pod contract

Specialist to work with Graham and Watkin Jones on major build-to-rent scheme

Banned building boss jailed for fraud

Court hears how disqualified director siphoned off cash from new housing company
3 days ago

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
6 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
6 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
6 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
6 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
6 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
6 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
6 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
7 days ago

Contractor services