HS2 phase 2 and Lower Thames Crossing delayed by two years

Aaron Morby 1 year ago
Share

The Government has pushed back starts on its two biggest planned infrastructure projects by two years in a bid to combat soaring inflation.

Government to announce project timings rethink imminently
Government to announce project timings rethink imminently

Transport secretary Mark Harper said the £7bn Birmingham to Crewe leg of HS2 and the £7bn flagship Lower Thames Crossing would be delayed to allow funds to be focused on delivering the existing capital programme.

He said: “Refocusing our efforts will allow us to double down on delivering the rest of our capital programme. This will place our transport investments on a sustainable footing and allow us to support the government’s priorities of halving inflation, growing the economy and reducing debt.”

The announcement casts into doubt progress on phase 2b from Crewe to Manchester, which looks likely to suffer a knock-on delay.

Harper said over £800m had already been spent on planning the massive Lower Thames Crossing tunnel scheme.

He said: “It is one of the largest planning applications ever, and it is important we get this right.

“We remain committed to the Lower Thames Crossing, and the development consent order process will be an important opportunity to consult further to ensure there is an effective and deliverable plan. In order to allow time for this process, and given wider pressures on RIS, we will look to rephase construction by two years.”

He also announced that the £320m A27 Arundel bypass in Sussex and £250m A5036 Princess Way in Liverpool were facing a range of challenges including environmental considerations and ongoing scope and design changes.

To provide more time, both these schemes will be deferred to RIS 3 (covering 2025-2030).

Harper said that other schemes earmarked for RIS 3 would continue to be developed, in line with the statutory process, but for consideration for inclusion during RIS 4 (beyond 2030).

“Given many of these schemes were previously expected towards the end of RIS 3, this extra time will help ensure better planned and efficient schemes can be deployed more effectively,” he said.

The big decision to delay progress on HS2 Birmingham to Crewe looks set to have an immediate impact on Kier and Balfour Beatty.

Kier has been mobilised to deliver a £50m highways and utility enabling works contract for this stage while Balfour Beatty is also working on its £52m advanced environmental works package.

Also bidders hanging on tenterhooks since September for news of the award of the £500m design and delivery partner role to oversee construction of phase 2a are likely to face an even longer wait to find out if they have succeeded.

Teams in the chase include: 2 Connect JV (AECOM /Costain Integrated Services);  AMS JV (Atkins /Mace Consult / SYSTRA); and Jacobs UK.

While a project delay is unlikely to save cash over the full course of the project, it will allow Government to spread the cost over a longer period of time, making it more affordable by reducing annual expenditure.

Last official forecast costs in October – HS2 update to Parliament


Stephen Marcos Jones, CEO of the Association for Consultancy and Engineering (ACE),  said: “I think every sensible person knows that global events have driven inflationary pressures to record highs.

“But we have already spent significant sums on the design and delivery of this transformational major project.

“Scaling back ambitions at this stage will mean the economic and social benefits of HS2 for communities across the UK is further watered down – and major delays like this are actually going to cost more in the longer term.

“In a nutshell, the delays announced today are, quite simply, an absolutely false economy.”

Latest news

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
2 days ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
2 days ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
2 days ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
2 days ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
2 days ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
3 days ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
3 days ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
3 days ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
3 days ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
4 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
3 days ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
4 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
3 days ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
3 days ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
4 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
4 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
5 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
4 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
4 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
4 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
5 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
5 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
5 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
6 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
5 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
6 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
5 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
6 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
6 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
6 days ago

Contractor services