Jackson signs £19m Sizewell C access roads deal

Aaron Morby 4 months ago
Share

Jackson Civil Engineering is the latest firm to secure an enabling works deal for the Sizewell C nuclear power station project ahead of a Government decision to go-ahead with main construction.

Early works well underway as industry waits for full go-ahead in Government Spring spending statement
Early works well underway as industry waits for full go-ahead in Government Spring spending statement

The firm will deliver key road schemes early in 2025 for the vast project.

The latest contract award was announced as Sizewell C confirmed it has already signed £2.5bn worth of contracts for the project spread around nearly 300 UK suppliers.

Pre-construction work and early enabling works got underway at the Suffolk site around 12 months ago after development consent.

Now the industry is waiting for the Treasury to approve the final business case, expected in the Spring spending revenue.

Sources close to talks between the Government and nuclear power generator EDF are reported to put the latest forecast cost estimate at £40bn, double the initial estimate provided by the power company.

The UK government and the EDF will fund about 40% of the Sizewell C project. Government officials are now gauging interest from private investors to meet the rest of the costs.

EDF yesterday issued a statement denying forecast project costs were so high.

“Recent claims about Sizewell C’s costs are not accurate and do not reflect the significant savings we are already making because we are building on the achievements at Hinkley Point C,” said EDF.

“That project has done the hard job of restarting UK nuclear construction and is seeing efficiency improvements of around 30% between its first and second reactor units.

“It means we are starting construction with a completed design, a skilled workforce and a supply chain ready to deliver.”


The 3.2GW nuclear power project will see UK firms deliver around 70% of construction value and support 70,000 high-quality jobs.

The project has already made significant progress across its main development site, including archaeology and earthworks, as well as the preparatory work for its concrete batching plant and temporary desalination plant.

New site offices on its Ancillary Construction Area are now complete, with enhancements to local road and rail infrastructure.

Julia Pyke and Nigel Cann, joint managing directors of Sizewell C, said: “It’s been an incredible first year of construction for Sizewell C.

“We’ve now got around 1,000 people driving this project forward both on our main development site and off-site infrastructure, and we’ll have around 2000 people by the end of the year with around double the amount of apprentices.

“We’re making big gains with early manufacturing, with equipment already 20% through manufacture. That means we’re already able to deliver significant contract value to suppliers and drive growth right here in the UK.

“Building on the work of Hinkley Point C, we have a fixed design and a capable and industrialised supply chain in place, and that gives us a big advantage when it comes to cost certainty and clarity of schedule.

“A year down the line of formal construction, we’re in a very strong position to deliver a project that will provide lower bills and clean energy to six million homes, thousands of good jobs, and energy security for Britain.”

Latest news

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
4 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
4 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
3 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
3 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
4 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
4 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
4 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
3 days ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
4 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
4 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
4 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
5 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
4 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
4 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
5 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
5 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
5 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
6 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
5 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
5 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
5 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
5 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
6 days ago

Morgan Sindall lands £30m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
6 days ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
6 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
6 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
6 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
6 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
6 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
6 days ago

Contractor services