Concrete problems hit Hinkley Point tunnels

Grant Prior 8 years ago
Share

Contractors at Hinkley Point will have to replace 150 cubic metres of concrete poured on the site as part of work to form tunnels to contain pipes and cables.

Aerial view of the north office and galleries under construction
Aerial view of the north office and galleries under construction

Problems have been identified in sections of the concrete base slabs constructed above the galleries sections of tunnels which will contain site infrastructure.

The Enquirer understands that the problem concrete is local to a small stretch of the 8km network of galleries tunneling.

Only 150 cubic metres of material are affected from the first 60,000 cubic metres poured on the site so far.

Nothing has been built on the slab and it does not form part of the foundations for the main nuclear power plant building where work is not due to get underway for 18 months.

A joint venture of Kier and Bam Nuttall is main contractor on the site earthworks package.

GetImage-1

Work underway last month in the galleries

Hinkley delivery director Nigel Cann said: “We have decided to replace a small area of concrete poured as part of the work to create tunnels for the pipes and cables.

“This is in line with the uncompromising attitude to quality taken at the Hinkley Point C Project.

“It is a very small proportion of the concrete poured on site so far and has no impact on the project schedule.”

Site Progress so far:

2,000 workers are on site every day, 65,000 meals every month needed to feed the growing workforce.

1,500 bed “Campus” accommodation for workers under construction with 500 beds on the site and 1,000 in Bridgwater – supplied by Newark-based Caledonian Modular .

76 apprentices are already working on the project, which will create up to 1,000 apprenticeships during the build.

4 million cubic metres of earth have been excavated – that’s enough to fill Wembley Stadium.

Two concrete batching plants are now complete. Up to 2,000 tonnes of concrete a day can be produced on site. At least 3 million tonnes of concrete will be used – 75 times more concrete than was used to build the Millennium Stadium in Cardiff.

10,000 tonnes of rock has already been delivered by ship from Pembroke, for the site’s new 13.5 metres high seawall.

29km of ground nails have been installed – enough to loop the perimeter of Hyde Park six times. The steel rods, each measuring up to 12 metres long, are used to stabilise the ground. A total of 110km will be used during construction.

Project remains on track to meet the 64% UK supply contribution with nearly £9bn of contracts signed since final approval. The latest contract with ABB Group was signed last month for the main power transmission systems for both reactors.

49 piles have been installed for the 500m temporary jetty in the Bristol Channel. Each pile – the foundation legs for the jetty – is 36 metres long, 3.6 metres in diameter and weighs in at 140 tonnes. The jetty will allow 80% of the aggregate to be brought in by sea rather than by road and is due to be completed next year. Devon engineering firm Blackhill worked on its largest-ever project involving 550 tonnes of steel for the jetty.

Dozens of cranes of all sizes are already on site alongside 200 pieces of large-scale construction equipment, ranging from excavators capable of moving 30 tonnes of earth in a single scoop to giant dumper trucks. The tallest ‘tower’ crane is 40 metres tall and can lift 16 tonnes. At peak construction there will be 50 ‘tower’ cranes at site.

£15 million is being invested into education, employment and skills to help inspire the next generation and provide people with the necessary training and support to help them into long term careers. Multi-million pound investments into a Construction Skills Centre and an Energy Skills Centre are not only ensuring that local people are equipped with the skills they need for the future, but helping to fill a national skills gap.

Latest news

Oxford United win green light for £150m all-electric stadium

Planners back 16,000-seat Kidlington ground with hotel, plaza and community hub
8 hours ago

Demolition record as eight cooling towers come down

Watch Brown & Mason set record at Cottam Power Station
21 hours ago

Hitachi Energy named for EGL3 converter station deal

Firm to build major HVDC converter stations in Aberdeenshire and West Norfolk
9 hours ago

PAS NW secures landmark £20m civils deal in Lancashire

Groundworks firm wins infrastructure for 429-home Wain Homes scheme
8 hours ago

Subcontractors wanted for jobs across the South West

Register now for latest Constructionline event in Bristol
8 hours ago

Profits double at Octavius as road and rail work grows

Recent acquisitions add to turnover growth at infrastructure specialist
1 day ago

Quarterly construction output growth masks orders slide

New orders down by over 8% driven by fall in infrastructure and offices
1 day ago

Vinci UK swings back into profit after group restructure

£166m cash injected to strengthen building and facilities operations balance sheets
2 days ago

Staged procurement to make comeback as pricing risk bites

Developers turn to staged deals to control costs on big-ticket commercial jobs
1 day ago

McGee profit halves as project start delays hit

Revenue up 24% but profits fall on higher carry costs
1 day ago

Vistry to deliver 2,300 homes at Rugeley power station site

139-acre brownfield site has already been extensively remediated
1 day ago

Andrew Scott wins role on Swansea’s next big office build

Contractor appointed for detailed design of 800-desk city centre hub.
1 day ago

Knights Brown to start £29m Poole flood wall job

1.5km barrier to protect homes and unlock regeneration plans
1 day ago

Kier lands £16m first ECI job with Southern Water

Design deal covers nitrogen cut and UV upgrade at Hampshire wastewater sites
2 days ago

Watkin Jones seals deal on 200-bed student scheme

Bristol project will involve four brick buildings rising to seven storeys
2 days ago

Severfield brings in new CEO from Laing O’Rourke ranks

Everton Stadium job chief Paul McNerney to take the helm in the autumn
2 days ago

Balfour hits 3% construction margin target

Profit target finally reached after eight years
2 days ago

Network Rail launches £240m OLE steelworks framework race

Deal to supply overhead line equipment for electrification schemes
2 days ago

Briefing starts for £8bn highways maintenance shake-up

National Highways launches early talks on next-generation regional roads upkeep
2 days ago

Plant hirer Lynch launches labour supply division

Workers now available to Tier 1 and Tier 2 infrastructure contractors
2 days ago

Kori lands latest £17m care home contract

Work to start on site in south west London next month
3 days ago

£70m Bristol student job finally gets Gateway 2 approval

Student developer Unite to progress two big schemes
3 days ago

Government unveils 10 new construction technical colleges

£100m plan to train 40,000 skilled trades by 2029 gets off the ground
3 days ago

McLaren lands London School of Economics £100m revamp

Central London job will be largest Passivhaus retrofit building in the UK
3 days ago

Industry standards body parts company with chairman

Considerate Constructors Scheme executive chairman also leaves role at Lighthouse Charity
3 days ago

Clegg wins car park to flats conversion contract

Work to start this autumn on transforming multi-storey car park into flats
4 days ago

Go-ahead for major retrofit of former London De Beers office

Mace advised on pre-planning construction plan for Hatton Garden gateway scheme
3 days ago

Danny Sullivan HS2 workers hit-out over agency moves

Site workers unhappy about how TUPE transfers are being handled
4 days ago

Overbury set for major law firm fit-out win

Contractor tipped for 2 Aldermanbury Square win
1 week ago

M&E contractor Cannock goes under

Supply chain takes hit as Staffordshire specialist goes down owing £4m
4 days ago