New Forth crossing steel sourced outside UK

Aaron Morby 13 years ago
Share

The construction consortium building the Forth Replacement Crossing has confirmed it will source the steelwork outside the UK.

Forth Crossing Bridge Constructors have placed a £790m contract for 37,000 tonnes of steel in the bridge with Chinese, Polish and Spanish firms.

The first fabrication is taking place at Crist in Gdansk, Poland which will produce 4,200 tonnes of steel to form the project’s massive caisson foundations.

Some 8,500 tonnes of steel bridge sections will be fabricated in Seville at Tecade-Megusa in Seville, Spain.

The vast majority of structural steelwork, some 24,500 tonnes, will be fabricated at Zhenhua Heavy Industries in Shanghai, China.

No Scottish firms bid to supply the huge amount of raw steel required by the project, although the final assembly stages of the steel components will be carried out on site at the new plants in Rosyth, South Queensferry and North Queensferry.

There are also unconfirmed reports that the massive cement contract is heading for a German company and not Lafarge’s nearby Dunbar cement works.

The bridge contractors secured the contract with a knock-down price of around £1.5bn, which came in £400m under budget.

Minister for Housing and Transport, Keith Brown said: “The FRC Principal Contract was procured under strict EU procurement law and awarded to FCBC at a price that delivered significant savings for Scotland’s capital budget.

“The steel fabricators that have successfully bid for these subcontracts were included within FCBC’s original tender submission and I am content that its proposals for sourcing steel represent best value for money for the public purse and are acceptable within the terms of FCBC’s contract.”

He added: “The British Chambers of Commerce has estimated the project’s knock-on economic benefits will be worth around £6bn and before Christmas it was confirmed the construction sector had already received a significant boost, with 118 sub-contracts worth over £20m in total already awarded to Scottish firms.

“The project is on schedule and within budget to open in 2016 and will safeguard a vital link in the country’s transport infrastructure.

“To ensure this remains the case it is vital that the very large amount of high-quality steel required by the project is produced and delivered in line with the demands of the construction schedule.

Construction will support over 1,200 jobs in Scotland.

Every year until completion in 2016, the construction will deliver 45 vocational training positions, 21 professional body training places and 46 positions for the long term unemployed.

Latest news

Spencer lands Scottish bridge hat-trick

Steelwork, gantries and bearing upgrades on Kessock, Forth and Tay crossings
11 hours ago

Completed buildings caught-up in Gateway 2 chaos

Developer distraught after dealing with Building Safety Regulator
20 hours ago

Aviva submits plans for 34-storey City office tower

Subject to planning work to start in autumn 2027
20 hours ago

Murphy takes 40% stake in Aussie civils contractor

Firm enters Australasian market with stake in Sydney-based contractor Abergeldie
1 day ago

Moat seeks firm for £420m repairs and maintenance deal

15-year deal to upkeep 20,000 south east homes
19 hours ago

Lynch takes over hotel for Sizewell plant operators

Hire giant now in the hotel business to guarantee accommodation for workers
20 hours ago

Subcontractors wanted across Scotland

Latest Constructionline event in Glasgow: Register now
19 hours ago

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
5 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
6 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
5 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
5 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
6 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
6 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
6 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
5 days ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
6 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
6 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
6 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
7 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
6 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
6 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
6 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
6 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
7 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
1 week ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
7 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
7 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
7 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
7 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
1 week ago

Contractor services