Roofer falls through skylight into empty swimming pool

Grant Prior 12 years ago
Share

A south London contractor has been prosecuted after a roofer plunged four metres through a skylight into an empty swimming pool.

The 45 year-old worker, Paul Shaw, of Maidstone, suffered multiple fracture injuries, including a broken right arm, when he fell through the roof opening which had been covered only with a thick plastic.

The incident on 29 February 2012 took place at a property in Tonbridge, Kent, where Bryen & Langley Ltd was the lead contractor overseeing the construction of an extension and swimming pool.

Maidstone Magistrates heard that an HSE investigation found that Bryen & Langley Ltd had failed to ensure that proper safeguards were in place to prevent anyone falling when work was underway at height.

The court was told that skylight openings above the swimming pool had been covered with plywood sheeting.

This was changed to thick plastic to allow some natural light through and to enable workers to lower materials into the pool area if needed.

The plastic was then covered with pallets and held down by timbers.

Shaw, who was employed by a roofing sub-contractor on site, went up to the swimming pool roof and stepped on to a skylight opening believing it was safe to do so.

The hole was simply covered by the plastic and he fell straight through landing on the pool’s concrete walkway.

He now has restricted movement in his wrist but was able to return to work after five months.

Bryen & Langley, of Eltham, London, was fined £12,000 and ordered to pay £9,209 in costs by magistrates after admitting breaching safety Regulations.

After the hearing, Inspector Melvyn Stancliffe said: “The distance that Mr Shaw fell could easily have resulted in his death. He is a lucky man – though I am sure he did not feel so at the time.

“This incident was avoidable and Bryen & Langley, as lead contractor, had a responsibility for safety on the site. It would have been a simple matter to have fixed the skylight covers in place.

“If they then needed to be moved for any reason, then temporary protection should have been placed around the openings and a system employed to ensure coverings were replaced promptly and correctly.

“Work at height needs to be properly planned and there need to be sufficient measures taken to guard against people falling.”

Latest news

£600m funding to train 60,000 construction workers

Government pledges massive cash injection to produce "site-ready" workers
1 day ago

Construction to start in May on £1bn port expansion

Work at London Gateway site will last four years
3 days ago

Green light for London Euston Tower rebuild

British Land says nearly a third of original tower will be retained
3 days ago

Contractors struggling to keep-up with demand for data centres

More than half of clients fear supply chain will struggle
3 days ago

Robert De Niro’s Nobu backs Manchester super tower

76-storey skyscraper will be tallest outside of London
3 days ago

PAC warns post-Grenfell policies threaten new homes goal

Watchdog MPs warn new build rates are being hit by diversion of funds to safety remediation
3 days ago

400 schools and hospitals to get rooftop solar panels

£180m investment is the first major project for Great British Energy
3 days ago

Legendre UK to convert Diageo HQ into hotel

Work to start this year transforming former home of drinks giant
3 days ago

Glencar wins phase 2 of Harwell tech scheme

Tech Foundry West will create 70,000 sq ft of lab and manufacturing space
3 days ago

Beard breaks company record with latest results

Family-owned firm posts best results for 133 years
4 days ago

United Living buys street lighting contractor

North West's Jones acquisition also strengthens power distribution offer
4 days ago

Deal to start £1.1bn British Library extension

Japanese developer takes control with aim to start construction next year
5 days ago

Fraud warning over bogus site supplies orders

Site temporary protection specialist sounds alarm after foiling scammers
4 days ago

Plan for world’s tallest energy-positive tower in Birmingham

£60m solar clad 29-storey tower will produce more energy than it consumes
4 days ago

Costain to lead on nuclear fuel site upgrade

Programme delivery partner role for upgrade to infrastructure at Capenhurst site
4 days ago

Willmott Dixon wins £32m Doncaster digital tech hub

Construction to start next month on Gateway One scheme
4 days ago

Pickstock to build Stratford resi tower

Construction set to start next year by modular builder owner
4 days ago

ISG accountants face investigation over audit

Watchdog launches probe into final accounts for collapsed contractor
5 days ago

Developer given suspended jail sentence for fire safety breaches

Director wrongly allowed residents to move into block before getting fire safety sign-off
5 days ago

Muse submits 1,600-home regen plan for Solihull town centre

Work to start early next year on Mell Square shopping centre redevelopment
5 days ago

Plans to be submitted for £140m Cardiff Central revamp

Enabling works to start this year to pave the way for construction
5 days ago

Developer fined after site hit with nine safety notices

Company "showed a total disregard to keeping its workers safe"
5 days ago

Ringway retains Hertfordshire highways after 12 years

Contract worth £55m a year and could be extended to 21 years
6 days ago

Driver pulls knife on Balfour Beatty road worker

East Sussex incident highlights dangers faced by highways staff
6 days ago

Wates starts £300m Suffolk prison expansion

Firm to build three house blocks at HMP Highpoint
6 days ago

Southern Housing seeks 10 firms for £1.7bn upgrade deal

South east fire safety and housing upgrade framework out to bid
6 days ago

Pothole patch-up policy fails as roads repair backlog hits £17bn

Industry calls for urgent mindset change on funding and maintaining local roads
6 days ago

Green light for 2,100 homes at old East London gasworks

St William secures S106 deal for world’s largest Victorian gasworks regen scheme
7 days ago

Lifting regs review bagged up with ‘bat and newt’ red tape purge

Government calls in regulators and tells Ofwat to speed up 30 major water projects
7 days ago

House builders call for rethink on Building Safety Levy

Developers call for spotlight to be turned on product manufacturers
7 days ago

Contractor services