Main bridge deck starts on £500m Mersey Gateway

Aaron Morby 8 years ago
Share

Contractors on the Mersey Gateway have started forming the first suspended section of the bridge marking a key milestone in the project.

Form traveller Mersey gateway gantry

Two of the six giant bridge building machines have been launched enabling construction of the 1,000-metre long reinforced concrete bridge deck across the River Mersey to get underway.

The 270-tonne machines act as movable concrete moulds, operating in a similar way to the Movable Scaffold System, which is building the elevated approach viaducts.

The form travellers were assembled at the south pylon earlier this year before being lifted to their starting position around 25m above the riverbed.

Construction teams then cast a pier table – a rectangular shaped platform – around the bridge pylon before preparing to start work on the main bridge deck.

Merseylink’s Kyuyoung Choi, operations manager for the main crossing, said: “Each segment of the bridge deck is made in the same way. Reinforced steel is placed into the mould and we then pour around 130 cubic metres of concrete inside to create each segment.

“From the third segment onwards, we install the connection boxes, which are called ‘delta frames’, for the steel stay cables, which are then attached to the upper pylon. The form travellers, which are powered by a hydraulic system, then move forward on a set of rails to the next position and the process is repeated.

“The deck segments are cast simultaneously, which allows the bridge deck to ‘grow’ from either side of the pylons until it meets the connecting bridge deck and the structure is complete.”

Three pairs of form travellers are being used to build the bridge deck with each pair operating as a unit. The machines will be launched from the north pylon later this month and from the central pylon during October.

Work on the bridge deck is expected to finish in summer 2017. During this time the form travellers will have cast a total of 154 deck segments between them. Each segment of deck will be around 33m wide and 6m long and will take around a week to construct.

The largest number of deck segments will be cast from the south pylon. There will be 33 segments between the south pylon and the south elevated approach viaduct, and 31 cast from the south pylon towards the central pylon.

The north pylon will see 29 deck segments cast on one side and 27 on the other, while 17 will be cast from either side of the central pylon.

The new bridge is on schedule to open in autumn 2017.

Latest news

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
2 days ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
2 days ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
2 days ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
2 days ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
2 days ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
3 days ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
3 days ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
3 days ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
3 days ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
4 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
3 days ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
4 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
3 days ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
3 days ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
4 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
4 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
5 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
4 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
4 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
4 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
5 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
5 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
5 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
6 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
5 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
6 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
5 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
6 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
6 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
6 days ago

Contractor services