Part of worker’s skull removed after 22,000v electric shock

Grant Prior 13 years ago
Share

Two North East construction companies have been fined after a worker suffered serious burns and an electric shock while working near overhead power lines.

John Dodsworth from Gateshead could have died without immediate emergency treatment and was taken to hospital by air ambulance.

He underwent several operations, including skin grafts and the removal of part of his skull – leaving extensive scarring.

Dodsworth was employed by James Kennedy as a pump operator and was working with Lumsden & Carroll Construction as they carried out modifications to sewers near Cockfield, County Durham in February 2008.

He was working in a compound pouring concrete into a mould to cast a sewer chamber lid. The pump had a 12 metre long boom to allow the hose to be positioned where required.

After the pour was finished the operator swung the boom round to return it to a parked position. But as he lowered it, it came into contact with overhead power lines crossing the site carrying 22,000 volts.

This caused  Dodsworth to receive a serious electric shock, suffering internal and external burns including to his hands, head, chest and legs.

Darlington magistrates heard Dodsworth still suffers constant pain which may be permanent and requires drug control meaning he may not be able to return to work.

An HSE investigation revealed that Lumsden & Carroll Construction could have either located the work compound elsewhere, so they did not have to work near the power lines at all, or used different equipment, not capable of coming into contact with the power lines.

After the case, HSE Inspector Martin Smith said: “Construction plant coming into contact with overhead power lines continues to be a frequent cause of incidents, which are often fatal. Mr Dodsworth is lucky to be alive and will have to live with the after effects of his injuries for the rest of his life.

“If it had been identified that working near the power lines was absolutely essential, then Lumsden & Carroll Construction Ltd and James Kennedy should have planned the work so that the pump was used sufficiently far from the power lines to prevent the incident and placed physical barriers and warnings at the site to control the work.

“James Kennedy should have made enquiries to ensure that the plant he sent was suitable for the site and that precautions had been taken against well-known risks.”

Lumsden & Carroll Construction was fined a total of £5,000 and ordered to pay £3,643.07 costs. James Kennedy,  who hired out the pump equipment, was fined £2,000 and ordered to pay £1,821.53 costs.

Latest news

Construction buyers see fastest growth for 14 months

Commercial building work leads the way in April
8 hours ago

Go Modular Technologies files administration notice

Southampton bespoke volumetric specialist employs around 60 staff
11 hours ago

Cladding firm went down owing supply chain £7.7m

Debts revealed at Everton stadium cladding contractor Alucraft Systems Ltd
11 hours ago

Rydon dogged by legacy fire safety remediation costs

£19m spent on fire safety remediation work to date
11 hours ago

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
4 days ago

Trio of builders win King’s Award for sustainability

Henry Brothers, Willmott Dixon and ZED Pods recognised for sustainability
10 hours ago

Kent police seize huge haul of stolen site tools

Hunt for power drill fitted with tracker busts tool theft ring
11 hours ago

Robertson names new Northern construction chiefs

Ian Phillips promoted and Ricky Brown joins from Morgan Sindall
11 hours ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
4 days ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
4 days ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
4 days ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
4 days ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
5 days ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
5 days ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
5 days ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
5 days ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
6 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
5 days ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
6 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
5 days ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
5 days ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
6 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
6 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
1 week ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
6 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
6 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
6 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
1 week ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
1 week ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
1 week ago

Contractor services