Spurs confirm stadium opening delay

Grant Prior 6 years ago
Share

Tottenham have confirmed their new stadium opening will be delayed due to problems with “critical safety systems.”

The club is now holding urgent talks with main contractor Mace and its subcontractors.

Site sources have been in constant contact with the Enquirer warning that the stadium would not be ready for the first planned Premier League game against Liverpool on September 15.

One said: “They have been chucking resources at this for months but it was never going to be ready.

A Spurs statement said: “Recent testing and commissioning has now shown issues with the critical safety systems.

“Urgent follow-up meetings with Mace and the trade contractors are now taking place. We are reviewing the situation and planned timetable to rectify and re-test, after which we shall be in a better position to outline a revised timetable.”

The club was hoping to hold test events on 27 August and 1 September which will now be rescheduled to “take place ahead of any first official match at the new stadium in order to achieve the safety licence.”

The Liverpool game and subsequent match against against Cardiff City on 6 October will now be switched to Wembley, as will the NFL match scheduled for 14 October.

Chairman, Daniel Levy, said: “We know this will be disappointing for all our season tickets holders, premium members and our fans worldwide.

“At the start of the project we asked for your support during what we knew would be a complex and challenging build and now we ask for your continued patience and forbearance.”

A Mace spokesperson said: “Unfortunately, our routine testing of the critical safety systems has flagged up issues that need to be addressed before the planned test events can go ahead.

“It is extremely disappointing that – as advised by the Club – a further two Premier League matches and the NFL game will now be played at Wembley, particularly for Tottenham Hotspur fans, but I am sure people will appreciate safety is our highest priority.

“The club and the construction team are working diligently to complete the iconic stadium as soon as possible.

“Although these delays are obviously frustrating, once complete the new stadium is going to leave a fantastic, lasting legacy and will be a project everyone involved will be proud to be associated with.”

Correction

The Qatari glazed roof manufacturer completed manufacture of all roof units for the Spurs stadium in June 2018. The Enquirer would like to apologise for any incorrect inference in an earlier version of this story that the glazed roofing units had anything to do with the delayed opening date.

Latest news

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
2 days ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
3 days ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
3 days ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
3 days ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
3 days ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
3 days ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
3 days ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
3 days ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
4 days ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
4 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
4 days ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
4 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
4 days ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
4 days ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
5 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
5 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
5 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
5 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
5 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
5 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
6 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
6 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
6 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
6 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
6 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
6 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
6 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
7 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
7 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
7 days ago

Contractor services