EastEnders set rebuild soars £27m over budget

Aaron Morby 5 years ago
Share

The BBC has been slammed for allowing the cost of the EastEnders set rebuild to spiral out of control.

Its E20 project to replace and enlarge the external EastEnders set and improve infrastructure at BBC Elstree Centre is now expected to cost £87m, rather than £60m as first planned.

The overall project will also take an extra two and a half years to complete.

Most of this increase relates to the higher cost of the Front Lot contract involving the rebuilding of Albert Square being delivered by Wates.

According to the spending watchdog, National Audit Office, the BBC now estimates this part will cost £56m – £23.5m more than planned.

The NAO takes aim at failures in the early planning stages where 70 late design changes were made and delays in the procurement process.

The project team also encountered asbestos and obstructions in the ground at various stages of the programme, which the NAO says should have been picked up with more detailed surveying work by spending more money during the planning phase.

The BBC had to switch from a single-stage tender in 2016 to two-stage bid process in 2017 because of limited market interest.

It then took 11 months for the BBC and Wates to agree on the final contract price from stage one selection, more than twice as long as planned.

This delay, higher than expected industry cost inflation, and new brick specification saw Wates’ fixed price contract agreed in August 2018 come in £9.5m more than consultant AECOM planned at £24m.

The BBC now expects the Albert Square rebuild to be completed at the end of March 2021, 22 months later than first planned in 2015, with the wider E20 project completed 31 months late.

Amyas Morse, head of the NAO, said: “The BBC will not be able to deliver value for money on E20 in the way that it originally envisaged. It is surprising that some of the reasons for this were built in from the beginning.

“Despite recent project management improvements, E20 is late and over budget against its 2015 plans. We believe that the planned benefits are still broadly achievable, but given the high-risk nature of E20 it will need close scrutiny until it is finished.”

Aerial view of Albert Square – the set for BBC’s Eastenders at Elstree Studios

The BBC built the external filming set for EastEnders in 1984, and originally planned to use it for two years.

It has lasted for 34 years but is no longer fit for purpose.

The poor condition of the set means the BBC cannot film in high-definition, degradation has led to increasing filming delays owing to stoppages in production due to health and safety concerns, and there are ongoing maintenance costs to ensure filming can continue.

Latest news

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
3 days ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
3 days ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
3 days ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
3 days ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
3 days ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
4 days ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
4 days ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
4 days ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
4 days ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
5 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
4 days ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
4 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
4 days ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
4 days ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
5 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
5 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
6 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
5 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
5 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
5 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
6 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
6 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
6 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
6 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
6 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
7 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
6 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
7 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
7 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
7 days ago

Contractor services