NAO slams Sellafield construction projects

Aaron Morby 13 years ago
Share

The country’s public spending watchdog has warned that Sellafield construction projects are running late and face serious uncertainty over final costs.

A critical report published today from the National Audit Office warns that six of the seven major construction projects at the huge site are behind schedule.

A long-term plan to clean up the Nuclear Decommissioning Authority-owned site was agreed last year after an earlier one stalled because it was “unrealistic”.

The NAO report found that after only 10 months of the new plan, performance in 12 of the 14 big buildings and equipment projects considered “critical” for reducing risk had been “dire”.

During this short time frame six of the seven major projects under construction accumulated delays of between two and 19 months.

Estimates for the total cost of these projects increased during this period by £294m with most of the cost escalation in the evaporator D project.

The report warns of gaps in the capability of Sellafield subcontractors and construction projects starting before design risks were sufficiently addressed.

The Authority estimates that £50m of the £244m increase in the cost of evaporator D and part of the 18-month delay since 2009 was down to the subcontractor lacking experience in welding to the necessary nuclear quality standards.

Margaret Hodge, who chairs the public accounts committee, said: “Projects of this length and ambition are ripe for dithering and delay.

“I am dismayed to discover the clean-up of Sellafield is no different. The authority’s revised plan sees critical milestones shunted back by up to seven years.

“My concern is that unless the authority holds Sellafield Limited to a clear and rigorously benchmarked plan, timetables will continue to slip and costs spiral.”

Around 240 of Sellafield’s 1,400 buildings are nuclear facilities and so far 55 buildings on the site have been decommissioned.

Latest news

Breakthrough for HS2 as first Birmingham tunnel section dug

Balfour Beatty VINCI completes 3.5km TBM drive in 652 days drive
3 hours ago

HS2 Curzon Street station redesign approved as timber roof axed

Change to meet stricter fire safety rules and cut maintenance costs
7 hours ago

Care home fire trial collapses

Prosecution withdrawn against four firms including Morgan Sindall Property Services
1 day ago

Leicester rebids £22m station revamp after failed tender race

Council opts for ECI route after receiving one bid for project
8 hours ago

Kier wins East Coast College rebuild job in Great Yarmouth

Work to start this summer for 1,300-student college
8 hours ago

R G Carter wins £28m hospital car park job in King’s Lynn

MSCP paves way for £1.5bn Queen Elizabeth Hospital rebuild in 2027
8 hours ago

London to relax green belt building rules

Sadiq Khan shifts position on planning
8 hours ago

Willmott Dixon wins Great Yarmouth waterfront deal

North Quay 10.5 acres mixed-use scheme to advance
1 day ago

SIG chief quits to join Travis Perkins

Gavin Slark to leave by the end of this year
9 hours ago

Eight take key spots on £250m Prosper framework

Housing and public building upkeep deal for North East awarded
1 day ago

Early call-out for £150m Ebbsfleet Garden City infrastructure

Bidders day to set out plan for Ebbsfleet Central commercial scheme
2 days ago

McLaren storms April contracts league with flurry of wins

Cardiff Bay Arena job headlines a series of big contract wins
1 day ago

Balfour Beatty lifts cash forecast after strong first quarter

Contractor set to hit £1bn average monthly net cash in 2025
1 day ago

Goldman Sachs-owned Adler & Allan buys 180-strong civils outfit

West Country's Glanville Environmental gets new owner
1 day ago

Caddick lands first contract for £200m Skelmersdale revamp

Developer gets green light for masterplan
1 day ago

Van Elle sells HGV fleet to haulage firm

WS Specialist Logistics pays £2.9m to take on fleet and drivers
1 day ago

Buyers more bullish about prospects for year ahead

Residential "resilient" but commercial work a weak spot
2 days ago

Council backs first Brutalist car park-to-flats scheme

Newcastle-under-Lyme multi-storey car park to be reborn as pioneering homes scheme
2 days ago

Hinkley Point C hits peak build with 26,000 jobs

3,000 more workers to join as fit-out work ramps up
2 days ago

Over 40 firms win Wessex Water M&E minor works deal

Broad sweep of specialists picked for AMP8 programme
2 days ago

Spencer lands Scottish bridge hat-trick

Steelwork, gantries and bearing upgrades on Kessock, Forth and Tay crossings
3 days ago

Winners revealed for £1.5bn decarbonisation deal

Fusion21 confirms places for 40 firms: Full list
2 days ago

Cladding firm fined £225,000 after fatal fall

Court hears how cherry picker didn't reach all parts of repair job
2 days ago

Completed buildings caught-up in Gateway 2 chaos

Developer distraught after dealing with Building Safety Regulator
3 days ago

Aviva submits plans for 34-storey City office tower

Subject to planning work to start in autumn 2027
3 days ago

Murphy takes 40% stake in Aussie civils contractor

Firm enters Australasian market with stake in Sydney-based contractor Abergeldie
4 days ago

Moat seeks firm for £420m repairs and maintenance deal

15-year deal to upkeep 20,000 south east homes
3 days ago

Lynch takes over hotel for Sizewell plant operators

Hire giant now in the hotel business to guarantee accommodation for workers
3 days ago

Subcontractors wanted across Scotland

Latest Constructionline event in Glasgow: Register now
3 days ago

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
1 week ago

Contractor services