The contractor will build 324 homes, just over half affordable, the rest for private sale. Construction is expected to start in the Autumn for completion in 2014.
The overall Wornington Green regeneration scheme, which is estimated to be worth over £250 million, will provide up to 1,000 homes and additional commercial space and will further integrate Wornington Green into the North Kensington neighbourhood.
Work on the further phases of the scheme will be awarded later in the year.
Programme
Phase 1a, starting August 2010 and lasting 16 to 18 months
1-28 Munro Mews
87-101 Wornington Road
Phase 1b, starting in 2011
Faraday House
Phase 1c, starting in 2012
Wheatstone House
Telford House
Lionel House
Kensington Housing Trust’s offices ad annex