Wates £100m London estate rebuild approved

Aaron Morby 14 years ago
Share

The London Borough of Bexley has approved plans to transform a high-rise estate in Erith with 620 low-rise homes.

Lead housing association Orbit has signed up Wates Living Space for the £100m regeneration project, which is due to start work in March once the first of seven tower blocks have been torn down.


One of seven high-rises due to be demolished

The first phase of the scheme proposes building 66 homes for sale, 82 for shared ownership and 195 for rent to create a mixed community, with the first homes ready in early 2015.

The plan, partly funded by the GLA, is designed to completely regenerate the Larner Road area and the five-year scheme represents one of the largest projects of its type in London.

Geoff Brocklehurst, Director of Architecture at Broadway Malyan, said: “The planning green light is a major milestone in the creation of a new family-friendly neighbourhood that will be safe, permeable and legible and is testament to our London-based team of design experts working in a close partnership with the client and wider project team.”

Latest project news

Kier and Tilbury Douglas win £108m schools double

Contractors picked for major DfE schemes in London and Eastbourne
3 weeks ago

Firms named to advance £89m trio of school jobs

Tilbury Douglas, McLaren and Willmott Dixon picked for DfE schemes
3 weeks ago

Morgan Sindall wins enabling deal on Plymouth Civic Centre retrofit

Council pushes ahead with first package on £50m landmark resi scheme
3 weeks ago

Bouygues bags £64m Crawley school rebuild

Work to start on three-year rebuild of Holy Trinity secondary school
3 weeks ago

Two JVs bag £1.5bn Anglian Water major projects deal

Ferrovial/MWH and VolkerFitzpatrick/Stevin land spots on new commercial delivery model
4 weeks ago

Costain bags £150m Thames Water wastewater programme

Firm to deliver improvement programme across 15 wastewater sites
4 weeks ago

Willmott Dixon cleared to rebuild RAAC-hit Stockport school

Work on £50m Bramhall High School job could start in January 2027
4 weeks ago

Taylor Woodrow breaks into Devon roads framework

Devon County Council refreshes £54m highways line-up for next four years
4 weeks ago

Lovell to start first phase of 450-home Horsham scheme

First phase of former pharmaceuticals site will retain Art Deco clock tower
4 weeks ago

Kier inks second Derwent London office scheme for £99m

Firm lands repeat business on flagship Oxford Street redevelopment
1 month ago

Willmott Dixon kicks off Oldham town centre regen

Firm picked for £28m first phase of Prince's Gate for developer Muse
1 month ago

Multiplex gets start date for City Road 36-storey tower

Main construction to get underway this quarter
1 month ago

Eric Wright to start £65m Tebay-style M56 services

Yates starts groundworks on Cheshire motorway services
1 month ago

Farrans to build new Stansted skylink walkways

Sections to be built "offsite" in vacant airport hangar
1 month ago

GMI lands £21m Nuneaton library and business hub job

Leeds contractor beats Clegg, McLaren and McPhillips to town centre regeneration scheme
1 month ago

GRAHAM wins final contract on £323m Didcot roads upgrade

Kelly Formwork picks-up bridge packages on project
1 month ago

Lovell wins job to rebuild Ilke Homes condemned estate

Fresh start for 221-home Southend scheme after modular homes bulldozed
2 months ago

Multiplex signs main works for £200m Derwent Baker Street job

Main works to start in 2027 on 236,000 sq ft West End scheme featuring pioneering concrete reuse
2 months ago

HG Construction go-ahead for Manchester student rooms

Gateway 2 approval for 239-bed purpose built student accommodation
2 months ago

Kier lands £98m double school build boost

Firm seals low carbon timber Lancashire academy and RAAC replacement school in Essex
2 months ago

Kier lands leading Piccadilly role for Crown Estate

Contractor to deliver 90,800 sq ft mixed use scheme in heart of London
2 months ago

Hochtief bags £250m Blackpool Silicon Sands data centre

First phase centres on a 6MW data centre with offices, research space and district heat network
2 months ago

Sisk lands £38m London Irish Centre rebuild

Work starts in January on three-storey Camden cultural and community hub
2 months ago

HBC wins 240-home Sheffield brewery site revival

Former Stones Brewery site to be transformed into homes after 20 years vacant
2 months ago

McLaughlin & Harvey lands £100m Rolls Royce deal

Construction to start later this year at Bristol research centre site
2 months ago

Kier wins £120m Brum roads extension amid PFI hiatus

New deal buys Birmingham two more years to resolve highways PFI stalemate
2 months ago

RED lands £42m Bristol and Bath office double

Firm to deliver Bristol's biggest office revamp alongside Bath HQ project
2 months ago

Mace to start £150m former London City Hall retrofit

Gensler redesign will straighten the building's distinctive leaning profile
2 months ago

HG Construction lands brace of student schemes

Contract wins from Fusion Group in Cardiff and Loughborough
2 months ago

Four firms land £300m Scottish electricity network deal

Quartet to upgrade network across north of Scotland
2 months ago